Removed two existing pumps, that where piped separately, thru a 12”, and 10” system:
Removed the two existing pumps, and piping systems, constructed a new 20” common pipe header , and are in the process of installing a single 14” pipe to serve two new pumps
New pumps will be taking condenser water from Lockheed Martin’s existing cooling tower to three water cooled chillers
Four to five week project
|