Lincoln Land Agra Energy
|
 |
| Location: |
|
|
| Owner: |
Lincoln Land Agra |
| General
Contractor: |
Lincoln Land Agra |
| Architect/Engineer: |
SSOE |
| Square
Footage: | |
| Construction
Cost: |
$40,000 | | Year
Complete: | 2007 |
| Scope of Work: | Plant Maintenance four day
turnaround: •
Hammermills: Change out bearing and perform motor/coupling alignment
• Whole Stillage Tank: Change out seals and perform motor/coupling
alignment • Slurry Blender: Change out seals and bearings
• Beerwell Pump: Replace seals and Bearings and perform motor/coupling
alignment • Grain Bucket Elevators: Replace on head and
tail pulleys • Drag Chain Conveyors: Replace Bearings,
Liners and flights • Screw Conveyors: Replace Bearings
| |