Corval
  Industrial Construction
 

Markets Served
sidelinkspacer
> Renewable Fuels
sidelinkspacer
> Power: Coal, Gas & Wind
sidelinkspacer
> Food & Beverage
sidelinkspacer
> Petrochemical
sidelinkspacer
> Biotech
sidelinkspacer
> Chemical Processing
sidelinkspacer
> Alternative Energy
sidelinkspacer
> Water & Waste Water
sidelinkspacer
- Other




Renewable Fuels Projects
thumb
 
thumb
 
thumb
 
thumb
 
thumbGranite Falls
CLS Building
 
thumbVerasun Energy Hartly
photo
 
 
thumb01   thumb02   thumb03   thumb03  
thumbfooter
Granite Falls CLS Building
heightener
Location:  
Granite Falls, MN
Owner: Granite Fall Energy
General Contractor: NewMech
Architect/Engineer: SSOE
Square Footage: 10,500
Construction Cost: $3,460,000
Year Complete: 2007
Scope of Work: NewMech was the EPC Contractor for the new Water Treatment Plant at the existing ethanol facility in Granite Falls. We self performed all of the piping, HVAC, setting of equipment, setting of tanks, field fabrication of tanks, and setting of structural steel.

The schedule on this project only allowed for 6 months of construction. The new CLS building was to be operational by the first of the year as mandated by the EPA. Greg Ross was the site Superintendent and saw to it that the facility was operational as needed in the short time frame that was given to us. We completed the project on time and within our budget. Great job everyone.