Food & Beverage Projects
thumb
 
thumb
 
thumb
 
thumb
photo
 
 
thumb01   thumb02   thumb03   thumb03      
thumbfooter
Summit Brewing Fermentation Tank Installation
heightener
Location:   Summit Brewing in St. Paul, MN
Owner: Summit Brewing
General Contractor: NewMech
Architect/Engineer:  
Square Footage:  
Construction Cost: $220,295
Year Complete: 2007
Scope of Work: Installed 6 New Fermentation Tanks in the existing brewery. Relocated 9 existing tanks and performed all new glycol piping to each tank.

For the setting of the new tanks, we had to make our top pick of the tanks through a hole in the roof of the brewery due to the size of the tanks and height issues inside the building. The work was performed on time and under budget. The owner was extremely happy with the performance of all involved.